System Conversion in short is typically the fastest option, an approach
that converts any SAP ECC 6.x system running on any database to SAP
S/4HANA, preserving your existing configuration, customizations, and
historical data. This approach allows a rapid technical conversion,
adding innovations gradually for users.
The major teams involved in a conversion project are the Technology Team
(responsible for executing the Software Update Manager(SUM) tool in all
the platforms(Sandbox, Development, Quality, Dry and Production)) ;
Functional Team (responsible for pre-check for Software Update Manager
compatibility, Functional factory, Migration to new Finance Tables,
Credit Management and Material Ledger activation, involving different
Lines of Business) ; Security Team (adjustment of roles for new Fiori
applications) ; the Advanced Business Application Programming (ABAP)
Team (responsible for the custom code adaption, SAP S/4HANA code
remediation etc.) and a Fiori Team (responsible for setting up the Fiori
Launchpad and Launchpad designer).
To begin with a conversion project, we first need to discuss and decide
on the data cleansing. This includes master data as well as
transactional data cleansing (Cleansing historical data) based upon the
customers’ statutory requirements. The data cleansing helps in reducing
the database size to be converted proving beneficial to the technology
team for a smooth conversion.
Starting with the Prepare phase, the base document to start with the conversion is the Readiness Check Report: (Transaction SE38 - execute /SDF/RC_START_CHECK)
Readiness Check is a high level analysis to get a Results Dashboard and
also download to a Results Document with details of Active Business
Functions, Add-On Compatibility, Custom Code Analysis, Recommended
Fiori Apps, SAP S/4HANA Sizing, Simplification Items, Business Process
Analytics and Data Volume Management.
The main elements that need to be analyzed from a functional point of
view are - Active Business Functions, Add-On Compatibility and
Simplification Items.
Active Business Functions – The active business functions, enable us to use specific new features and enhancements for our various business processes.
In SAP S/4HANA business functions can have the following status:
'always_on' , 'customer_switchable' , and 'always_off' . This results in
the following behavior during the system conversion:
- If a business function was switched on in the start release
system, but defined as 'always_off' in SAP S/4HANA, on-premise edition,
then a system conversion is not yet possible with this release at the
current point in time.
- If a business function was switched off in the start release
system, but defined as 'always_on' in the target release, then the
business function will be automatically activated during the conversion.
(Data Source – SAP Note
2240360 and
2240359 )
Add-On Compatibility – The check analyzes how many
add-ons are installed in the system, with the help of a Maintenance
Planner whether they are compatible with SAP HANA.
The Add-Ons existing on a customer’s SAP ECC system that shall be part
of the target SAP S/4HANA release must be supported in order to permit
the system conversion/upgrade process to go through.
The Maintenance Planner is a solution hosted by SAP that helps you plan
and maintain systems in your landscape. The Maintenance Planner also
helps the customer get a view on the compatibility status of the Add-Ons
on his/her SAP ECC system before system conversion/upgrade to SAP
S/4HANA.
Please refer
https://blogs.sap.com/2021/03/15/handling-add-ons-during-a-system-conversion-to-sap-s-4hana/ for detailed description on handling Add-ons during system conversion.
Simplification Items – By executing the above mentioned
report you can get a list of Simplification Items that are relevant to
the specific customer database and must be looked into before converting
the SAP ECC system to SAP S/4HANA.
Below is how the Simplification Items List, post execution of the Readiness Check Report in SE38 looks like:
(Image Source: SAP)
The column 'Relevance' describes the relevance of the item (relevant/
not relevant/ relevance cannot be determined(execute the check
manually)).
The second column talks about the consistency of the item
(warning/error/resolved/inconsistent). The Items with errors and
warnings are the ones that need to be looked into and resolved before
moving for conversion. There is also an option for exemption of the
simplification items. This can be applied to the items that can be
covered post conversion and would not impact the Software Update Manager
run in any ways.
Each Simplification Item has a reference SAP Note that explains how to
proceed in resolving the specific item. Referring to the corresponding
notes, a consultant can easily proceed with the resolution of the open
simplification items.
The Conversion works in three phases at a high level:
Pre-Conversion --- Software Update Manager (executed by technology team) --- Post-Conversion
Pre-Conversion and Detailed Assessments:
The resolution of the Simplification Items is a pre-conversion activity.
From Logistics side, most of the activities are Pre-Conversion, whereas
for Finance, we have a lot of involvement during Post-Conversion as
well. During this phase we conduct Detailed Assessment Sessions with the
customers, introducing them to the possible changes that might directly
or indirectly impact the business process once the system is converted.
Fit-Gap Analysis:
This is an important milestone, where the changes and their business
impact is discussed in detail with the customers. There are certain
optional changes as well that are a part of conversion and should be
explained to the customer in the As-Is and To-Be format in order to
provide an opportunity to the customer to decide whether they want to
proceed with the To-Be process or if they are okay with the current
process and want to perform it As-Is. Another important decision that
need to be discussed and taken is on the Fiori apps. Post conversion
there are certain FI transactions that would become completely obsolete
and would be replaced by Fiori. Along with the mandatory applications,
customers also have a choice to implement Fiori apps for transactions
that are still supported in SAP S/4HANA as well. These discussions can
be conducted during the Fit-Gap Analysis sessions.
Software Upgrade Manager (SUM):
Post Completion of the identification and resolution of the
Simplification Items, Basis team executes the SUM (Software Upgrade
Manager) tool - a multi-purpose tool that supports various processes,
such as performing a release upgrade, installing enhancement packages,
applying Support Package Stacks, installing add-ons, or updating single
components on SAP NetWeaver.
Post-Conversion:
Following the Software Update Manager Conversion, next comes the turn of
the post-conversion activities. These include the manual data
migration, custom Code adaptions, any Workflows, Reports, Interface,
Conversion, Enhancements and Forms (WRICEF) implementations that are
required as part of the customer requirements and the system landscape.
Along with the above, the consultants are also required to prepare
configuration document/run book that can further be used as a guide to
understand the major configuration changes that have been conducted as
part of the conversion.
Once we are done with the Post-Conversion Activities we proceed with the
testing. This process is applicable for all the landscapes (Sandbox,
Development and Quality). In Sandbox, we perform a smoke test, in order
to test the basic transactions and functionalities. Similarly, in
Development, we perform a round of unit testing. Once the Quality system
is converted, System Integration Testing(SIT) and User Acceptance
Testing(UAT) is conducted from the customer’s end (with the support of
SAP).
Cutover Plan:
Post the System Integration Testing(SIT) and User Acceptance
Testing(UAT) Sign-off, we start with the cutover planning. This includes
a planned timeline for all the relevant actions to be performed in the
dry run and the Production system to implement the final SAP ECC to SAP
S/4HANA Conversion. The cutover plan includes the responsible Lines of
Business's points of contact and their activities timed and planned in
order to have a smooth and successful conversion.
Thus, to conclude, a successful conversion to SAP S/4HANA can be
conducted if the above mentioned key points are considered and well
looked into.
For more information on topics relevant to SAP ECC to SAP S/4HANA Conversion please do refer the below:
https://blogs.sap.com/2020/05/27/sap-s-4hana-1909-system-conversion-steps-details-how-to-be-prepared...
https://blogs.sap.com/2020/02/12/sap-s-4hana-1909-post-conversion-tips-and-suggestions/
https://go.support.sap.com/roadmapviewer/#/group//roadmap/BWHANATRANSONPRE/node/901B0E6D3F501ED78596...
Thank you!